Keel Gantt at 10,000 work items

Measured 18 and 21 November 2026

We built a Jira project with exactly 10,000 work items and timed Keel Gantt on it, on a live Jira Cloud site, with the clock that is built into the app.

 Time
All 10,000 work items on screen and editable3.2 to 4.9 seconds
All 9,654 dependency arrows drawn as well7.8 to 10.9 seconds
A 2,000-item plan, start to finish2.2 seconds
Re-opening a plan you have opened beforeBars appear as soon as the app has started
Dragging a bar, scrolling, turning on the critical pathNo waiting at 10,000 items

Nine runs over two days, in two browsers. The range is the fastest and slowest of them.

What we measured

What makes it slower or faster

The two halves of the load behave differently:

You can keep editing while dependencies are still loading. The critical path waits until they are all in, so that it is never worked out from half the picture.

Check it on your own plan

Every Keel Gantt chart shows its own load time, on your data, on your site. Open the Gantt tab, press Refresh, and read the label above the work item list. Hover over it for the detail: how many items, how many requests, and how long each part took.

Why it is fast

What it does not skip

Speed does not change the safety rules. Nothing is written to Jira until you press Save and confirm the list of changes. Only start and end dates are ever written. Save re-reads Jira first, and an item a teammate changed since you edited it is held back for you to decide.

Limits